Greenway USA was contracted to install new exterior lighting along Morris Park Ave in the Bronx as part of a capital improvement and security project for the College. 

The scope of work involved the excavation and installation of poles, pole bases and related conduit and power wiring.  Heavy rock excavation was encountered and the penetration/waterproofing of Forchheimer Building foundation was required to secure new power for the lighting and low voltage cabling for the security cameras source from basement of building.  New security cameras were installed on new light poles to allow Einstein Security a better view of area prone to crime.  Site was regraded and landscaped.

Greenway USA would like to thanks the Albert Einstein College of Medicine for the opportunity to work on this project!   